Business Type:
Manufacturer/Factory
Establishment:
2012
R&D Capacity:
ODM, OEM, Other
OEM/ODM Service
Sample Available

Automatic Welding Machine for Pipe Fabrication, High Pipe Welding Machine, Automatic Pipe Welding Machine manufacturer / supplier in China, offering Automatic Pipe Spool Fabrication Line/Pipeline Prefabrication Automatic Welding Center, Pipe Spool Fabrication System/Fabrication Line/ Pipe Fabrication Line, Simple Type Jacking System/Tank Construction Equipment/ Desulfurizing Tower Jacks and so on.

1
    YRS
General Supplier
Supplier Homepage Auto, Motorcycle Parts & Accessories Auto Repair Equipment & Tools Lifting Jack China Hydraulic Jacking System for Tank Construction Machinery Automatic CNC Hydraulic Lifting System-China Tank Farm Construction Solution

China Hydraulic Jacking System for Tank Construction Machinery Automatic CNC Hydraulic Lifting System-China Tank Farm Construction Solution

Get Latest Price
Min. Order / Reference FOB Price
1 Piece US $150000.00/ Piece
Local Area: Jian, Jiangxi, China
R&D Capacity: OEM, ODM, Other
Payment Terms: LC, T/T, PayPal
Type: Hydraulic Jack
Structure: Hydraulic Jack
Capacity (Load): 21-30T
We are able to provide complete solution for tank welding with different construction method, both bottom-to-top and top-to-bottom tank construction, hydraulic lifting system are especially designed for top-to-bottom tank erection.
The following short description gives the working procedure in outline. It can in certain details be modified when required.

Step 1. The tank bottom - plates are placed on the prepared foundation and welded together.
Step 2. The beams or lattice work of the roof are assembled and finally joined to the upper rim of the shell ring.
Step 3. The jacking equipment is installed in the tank. The plates of the second shell ring (next to the top ring) are positioned outside the first one.
Step4.The completed part of the tank (roof and top shell ring) is lifted hydraulically to a height at which the plates of the second ring can be moved into place and the roof sheeting can be completed.
Step5.The plates of the second shell ring are located exactly and welded together to the lower edge of the first ring.
Step6.The plates of the third shell ring are placed outside the second shell ring.
Step7.The completed part of the tank (roof the two uppermost shell rings) is lifted.
Step8.The above cycle of operations is repeated until the last (bottom) shell ring is finished.
Step9. The entire tank is lowered down to the bottom plate and welded to this.
Step10. The lifting equipment is dismantled.